4CM were called back by Exolum to their Backford aviation fuel terminal near Chester for a second phase of road works: critical C40 concrete repairs on the live jet road, and new kerbing and resurfacing on the emergency fire access road, with the terminal live and trading throughout.

Location

Backford, Chester

Industry

Aviation Fuel (COMAH)

Type

Groundworks, Concrete & Surfacing

Duration

Oct – Nov 2026

Role

Principal Contractor

The Requirement

Exolum’s Backford terminal is a COMAH-regulated aviation fuel site on the company’s UK pipeline network, storing and delivering fuel for around 40% of flights leaving the UK. Its jet road is the live loading route where road tankers collect jet fuel for airports across the country and the Ministry of Defence. Having delivered carriageway repairs, kerb realignment and a new tanker layby at Backford in summer 2026, 4CM were asked back for more critical repairs to the jet road and a large section of new kerbing and tarmac on the emergency fire access road.

The fuel could not stop. The jet road had to stay open to tankers of up to 44 tonnes at all times, with no closures or diversions, and the fire access road could never leave the terminal without emergency access. Every task also had to run under Exolum’s COMAH, hazardous-area and permit-to-work controls.

Our Solution

Working as Principal Contractor under CDM 2015, 4CM delivered the works with the terminal live throughout, including

  • Four failed jet road bays (31m²) saw-cut, broken out and rebuilt in 200mm C40 concrete on a 200mm MOT Type 1 sub-base, DPM and two layers of A393 mesh
  • Steel road plates and a dedicated, radio-linked traffic marshal kept a lane open past every bay, so the jet road never closed to tankers
  • 96m of new HB2 half-battered kerbs on a C20 concrete bed and haunch along the fire access road
  • Corner radius widened by 1.2m over a 15m sweep for easier access for fire appliances
  • 185m² of 100mm AC20 binder laid in a single course and rolled, one section at a time, with kerb trenches backfilled the same day so the emergency route was never left open overnight

Outcome

Exolum’s tankers kept loading throughout the works, with zero jet road closures, so jet fuel kept moving to airports and MOD sites without interruption. The jet road now has four rebuilt, HGV-grade concrete bays, and the fire access road has a kerbed, resurfaced running surface with a wider corner, giving the emergency services better access across the terminal. Another phase delivered for a return client, with the site live and trading at all times.